Construction Updates
Get a detailed overview of the current status and progress at our construction sites
September 2024
- Retaining wall casting from 1st basement to GF level for Pour 2
- Columns and lift walls steel binding, shuttering and casting from 1st basement to GF level for Pour 2.
- Columns and lift walls steel binding, shuttering and casting from 1st basement to GF level for Pour 3.
- Slab shuttering, steel binding and casting for Pour 4 in 2nd basement slab area.
- columns layout and steel binding in progress for Pour 4, from 1st basement to GF level
August 2024
- 2nd pour of 2nd basement slab shuttering & steel binding in progress
- 2nd pour of 2nd basement slab casting in progress
- 3rd pour of 2nd basement slab shuttering & steel binding in progress
- 3rd pour of 2nd basement slab casting in progress
- 1st pour of columns and retaining wall from 1st basement to ground floor casting done